Okay, another status report.

All issues for the 0.5 release have been resolved/closed, and  
currently all unit tests pass.  Please consider SVN locked down until  
further notice.  (It's 4:30am, and I don't trust myself to do the  
release correctly at this time without some rest.  I'll start the  
release process in a few hours.)

Thanks for your patience, everyone.  I'm really happy that our Getting  
Started examples are using our own JCR implementation and are using  
federation to boot.  Stay tuned, 'cause there's more to come in a few  
hours.

Best regards,

Randall

On Jun 10, 2009, at 12:24 AM, Randall Hauch wrote:

> Just a quick status to let everyone know how the release is going.
>
> We've spent the last few days completely rewriting and reorganizing  
> the Getting Started and Reference Guide documents.  I'm very proud  
> of the work that we've done with them, because they really are much  
> improved.  The Getting Started document is a little smaller and more  
> targeted toward an initial quickstart, while the Reference Guide has  
> been expanded a great deal and now documents a lot of the different  
> parts of JBoss DNA.
>
> In my testing this evening, I discovered an issue (DNA-449) with the  
> federation connector which stemmed from recent changes to the  
> configuration.  I plan to fix this tomorrow morning, then update a  
> few screenshots in the Getting Started doc (DNA-446), and follow  
> that up with final integration testing and (if everything goes well)  
> the final build and release process.  Then, of course, the emails  
> and blog post with the announcement.
>
> Thanks to Brian and Serge for their help over the last few days.   
> There's a little more work to do, but we're almost there.  More to  
> follow tomorrow.
>
> Best regards,
>
> Randall
>
> On Jun 7, 2009, at 6:56 PM, Randall Hauch wrote:
>
>> I spent much of this weekend reorganizing the Getting Started  
>> document to better reflect the current state of the project as a  
>> JCR implementation, to add documentation for the new configuration  
>> mechanism, and to remove portions that are already (and better)  
>> covered by the Reference Guide.  (In fact, there was a fair amount  
>> of duplication between the two documents, so most of this has been  
>> removed.)  I still need to complete my editing of the Reference  
>> Guide.  Frankly, both documents needed more love than I had  
>> anticipated, mostly because of the new configuration mechanism.   
>> We're getting close, but there are a number of small loose ends.
>>
>> So I'd like to propose trying to release 0.5 this coming Wednesday  
>> (June 10).  This will give me enough time to wrap up my edits of  
>> the documents, plus it will give Brian the time he wants to finish  
>> the work on the RESTful web app and corresponding documentation,  
>> which will be a great addition.  In the meantime, I would  
>> appreciate some reviewing/editing of the updated Getting Started  
>> guide (and soon the updated Reference Guide, after you hear from  
>> me).  If you find any mistakes, go ahead and log bugs in JIRA.  And  
>> if you can fix it, go ahead and make the changes in the DocBook  
>> source within SVN.
>>
>> Any objections or suggestions otherwise?
>>
>> Best regards,
>>
>> Randall
>> _______________________________________________
>> dna-dev mailing list
>> dna-dev at lists.jboss.org
>> https://lists.jboss.org/mailman/listinfo/dna-dev
>
> _______________________________________________
> dna-dev mailing list
> dna-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/dna-dev




More information about the dna-dev mailing list