[infinispan-dev] Infinispan 7.1 plan

Tristan Tarrant ttarrant at redhat.com
Mon Oct 20 10:47:31 EDT 2014


Hi guys,

with the imminent release of 7.0.0.CR2 we are reaching the end of this 
release cycle. There have been a ton of improvements (maybe too many) 
and a lot of time has passed since the previous version (maybe to much).
Following up on my previous e-mail about future plans, here's a recap of 
a plan which I believe will allow us to move at a much quicker pace:

For the next minor releases I would like to suggest the following strategy:
- use a 3 month timebox where we strive to maintain master in an "always releasable" state
- complex feature work will need to happen onto dedicated feature branches, using the usual GitHub pull-request workflow
- only when a feature is complete (code, tests, docs, reviewed, CI-checked) it will be merged back into master
- if a feature is running late it will be postponed to the following minor release so as not to hinder other development

I am also going to suggest dropping the cherry-picking approach and going with git merge. In order to achieve this we need CI to be always in top form with 0 failures in master. This will allow merging a PR directly from GitHub's interface. We obviously need to trust our tools and our existing code base.

This is the plan for 7.1.0:

13 November 7.1.0.Alpha1
18 December 7.1.0.Beta1
15 January  7.1.0.CR1
30 January  7.1.0.Final


Tristan



More information about the infinispan-dev mailing list