[infinispan-dev] 9.1.0 endgame
Tristan Tarrant
ttarrant at redhat.com
Wed Jun 21 08:19:18 EDT 2017
The release wrangler for 9.1.0.CR1 will be Will.
Will willl (haha !) perform the release on the 29th. This is a hard date.
Tristan
On 6/19/17 12:22 PM, Tristan Tarrant wrote:
> Hi all,
>
> I have updated Jira with the next milestones for 9.1.0
>
> 9.1.0.CR1 - 30th June
> 9.1.0.Final - 14th July
>
> This extends the traditional minor-release timebox by two weeks,
> essential because the features we wanted for Beta were a bit late.
>
> From now until the end we should only consider features whose PR have
> been open for a while (e.g. scattered cache). Bug fixes and minor
> enhancements to existing features are obviously allowed.
>
> Anything else will need to be shunted to 9.2.0.
>
> Tristan
--
Tristan Tarrant
Infinispan Lead
JBoss, a division of Red Hat