"ALRubinger" wrote :
| So now AS requires Dependency Version 2, which breaks EJB3. CR1 is held up because a switch was flipped right before the milestone, and EJB3 needs to resolve the errors before CR1 can ship.
|
That coordination should have happened before the shared pom was updated. Each project should have a subtask on the jira issue for updating the parent pom to version 2, and only when those are closed the parent is updated.