On 02-03-2009 15:39, Jason T. Greene wrote:
> The AS 5.1 community schedule has been updated to account for the
> embedded console time-line. Essentially an additional month was added
> to the CR1 phase. The new dates are as follows:
>
> 5.1 Beta1 (Same)
> ---------
> Primary Goal: Completion of profile service work necessary for the
> console
Would "completion of profile service work necessary for the tools" be
covered by this too ?
My guess is no - but just ask asking ;)
/max
> Secondary Goal: Introduction of New Components (Web Beans Preview, JDK
> Logging, JBoss Threads, Bootstrap) & Misc Updates (EJB3, JPA,
> security, clustering, Web Services)
>
> Code Freeze: March 9th
> Release: March 16th
>
> 5.1 CR1 (Shifted)
> -------
> Primary Goal: Inclusion of a working console for community testing
> Secondary Goal: Inclusion of JBM2 tech preview
>
> Code Freeze: May 12th
> Release: May 19th
>
> 5.1 GA (Shifted)
> -------
> Primary Goal: Shipping the first release with a real admin console
>
> Code Freeze: June 8th
> Release: June 15th
>