[jboss-dev] Accelerated 5.1 Timeline (New Dates!)
Dimitris Andreadis
dandread at redhat.com
Wed Mar 18 09:08:48 EDT 2009
I guess, now!
Max Rydahl Andersen wrote:
>
> At what phase/time-period would tools requirements be discussed ?
>
> Last time we said early april but with this schedule is there any room
> for that ?
>
> /max
>> Due to recent changes in the EAP5 schedule, we have had to
>> significantly pull in our community dates. The new CR1 and GA dates
>> are as follows:
>>
>> CR1
>> ---
>> Code/Component Freeze : April 20th
>> Final Console Inclusion : April 22nd
>> Release : April 27th
>>
>> GA
>> --
>> Code/Component Freeze : May 11th
>> Release : May 25th
>>
>>
>> There is now only 1 goal, and that is meeting our dates with a working
>> console.
>>
>> This also means profile service work is the priority:
>> https://jira.jboss.org/jira/browse/JBAS-6620
>>
>> All other updates are a nice to have, and if you want them included in
>> 5.1, they need to be done as early as possible.
>>
>
> _______________________________________________
> jboss-development mailing list
> jboss-development at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/jboss-development
More information about the jboss-development
mailing list