The time line for the final releases of JBoss AS 6 as follows:

6.0.0.CR1:
Code Freeze: November 10
Release Target: November 15
Component Upgrades: https://jira.jboss.org/browse/JBAS-8253

This release will focus on the remaining work needed for EE 6 Web Profile compliance.


6.0.0.Final:
Code Freeze: December 10
Release Target: December 17
Component Upgrades: https://jira.jboss.org/browse/JBAS-8086

The Final release time is limited and is intended to Resolve Major JIRA issues and finalize community documentation.
 

Be sure to file a subtask if you are planning on a component upgrade.  Component upgrades will be reverted due
to regression, destabilization, or impact to the certification effort. 