We have a need for process designers to place nodes in their processes to pattern a milestone that fulfills some reporting needs. For instance, they may want to report on what date each instance of a process started and then on what date each of their their milestones were reached.
Is doing this as a plain "Node" the best way to achieve this? And then to gather the execution data from the JBPM_LOG table? My only concern about this approach would be filtering out Nodes that may have been utilized to execute logic and weren't placed there to serve as milestones.
Thanks!
Paul
View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4158480#4158480