Hi Tihomir,
thanks for the tip, but that's exactly I'm trying to avoid, because I'm going to have a lot of my custom "waiting work items" (e.g. wait 1 day, then do something, wait next 5 days, do something else, wait next 10 days etc), and for each of them I'll have a separate intermediate event to trigger it.
Ideally, I'd like my custom work item handler to be able to respond to a signal event, giving me ultimate control over my custom work items and minimizing number of nodes. Does anybody know is there a way to "connect" custom work item with a intermediate signal, so that when I call signalEvent(), my custom work item handler's executeWorkItem() method is called?
I'm still a newbie in BPMN, so please pardon if the question is stupid.
Thanks,
Miljenko
--------------------------------------------------------------
Reply to this message by going to Community
[http://community.jboss.org/message/629012#629012]
Start a new discussion in jBPM at Community
[http://community.jboss.org/choose-container!input.jspa?contentType=1&containerType=14&container=2034]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.jboss.org/pipermail/jboss-user/attachments/20110929/a3e5c0b1/attachment.html
More information about the jboss-user
mailing list