We had a call earlier today discussing how to steer the delayed 3.2.1.CR2 (assumed to become final) and 3.2 M2

The short version is that 3.2.0.M2 stays as planned and we shift/bend 3.2.1.CR2 around it.

That gives the following schedule:

1st June: 3.2.1.CR1pushed out to staging today (Nick will post about that when it happens)

14th June: 3.3.0.M2 code freeze

~16th June: 3.3.0.M2 build candidate for QE/smoketesting

19th June: What's'new Ready for review/assembly

22nd June: 3.3.0.M2 release (together with AS7/Eclipse Indigo)

27th June: 3.2.1.CR2 Codefreeze

~30th June: 3.2.1.CR2 build candidate for QE/full testing on staging

~15th July: 3.2.1.Final rebuild / release

I'll get jira updated tonight/tomorrow to reflect these dates.

/max