Folks,
starting with jbpm-3.2.3.GA we will have a release cycle of eight weeks per minor release. The motivation is to improve the predictability of the jbpm releases, therefore we will follow the following rules:
| ---------------------------------
| W1
| W2 Define set of JIRA issues (Jira Freeze)
| ----------------------------------
| W3
| W4
| W5
| W6 Work on issues (Code Freeze)
| ----------------------------------
| W7
| W8 QA, Docs, Packaging (Release)
| ----------------------------------
|
In other words, at the end of W2 there are no more JIRA issues added to a release. At the end of W6 there are no more code changes.
Please check out the road map for for upcoming releases.
http://jira.jboss.com/jira/browse/JBPM?report=com.atlassian.jira.plugin.system.project:roadmap-panel
Cheers
View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4160921#4160921
Reply to the post : http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&p=4160921
More information about the jbpm-dev
mailing list