For this proposal, I think the following timeline is achievable:
Milestone 1 (approx 7 days): Get overview of the jBPM codebase and learn the build system.
Milestone 2 (approx 12 days): Work out the simplest possible example and discuss the proposed solution. Starting points: add a property to the deployment (probably as an attribute in the process definition). Add process instance migration code to the JpdlDeployer.
Milestone 3 (approx 7 days): Add a translation map in case activity names have changed. Define how this mapping information will be part of a deployment.
Milestone 4 (approx 15 days): Analyse exact constraints for migrating process instances over to a changed process definition. What kind of changes can be handled. And what kind of changes cannot be handled. Add those constraints to the process instance migration.
Milestone 5 (approx 15 days): Develop a testing strategy for process instance migrations.
View the original post : http://www.jboss.org/index.html?module=bb&op=viewtopic&p=4222989#4222989
Reply to the post : http://www.jboss.org/index.html?module=bb&op=posting&mode=reply&p=4222989
More information about the jbpm-dev
mailing list