    You 'll want incremental score calculation (with delta's) for your
    "end times".<br>
    &nbsp;
<a class="moz-txt-link-freetext" href="http://docs.jboss.org/drools/release/5.4.0.Final/drools-planner-docs/html_single/index.html#incrementalScoreCalculation">http://docs.jboss.org/drools/release/5.4.0.Final/drools-planner-docs/html_single/index.html#incrementalScoreCalculation</a><br>
    <br>
    So that naturally puts the calculation of those end times in the
    scoreDRL (or IncrementalJavaCalculator if you're not using drools).<br>
    Whether or not that endTime should be a property on the model (at
    least the model that Planner works with), is an open design
    question.<br>
    If it isn't, you can use insertLogicals in DRL, like I did in
    nurserostering to calculate the number of sequential weekends being
    worked etc.<br>
    If it is a property on your model, either the DRL must first
    "correct it" (with higher salience rules for example),<br>
    or custom moves must "correct it" as they are being done (which is
    very hard as it entails constraints functionality).<br>
    <br>
    As for the cloning: it's quite simple:<br>
    Either the model's entity contains the endTime property, then clone
    it.<br>
    If it doesn't, then there's nothing to clone.<br>
    I don't see any problems related to the cloning.<br>
    <br>
    <div class="moz-cite-prefix">Op 18-08-12 01:53, Josef Bajada
      schreef:<br>
    </div>
    <blockquote
cite="mid:CAJOvgLLHsw=iv19B=h3Uev9UEaONCKsg2SfX8EhAPjNV7FVrGA@mail.gmail.com"
      type="cite">Hi Geoffrey,
      <div><br>
      </div>
      <div>Following your advice and after gaining some more
        understanding of planner, I think approaching the problem as a
        chain of tasks one of the other makes sense. It would have some
        'wait' time between tasks where the end time of the previous
        task is smaller than the minimum time the task has to wait after
        its dependency (which could be different from the previous
        task).</div>
      <div><br>
      </div>
      <div>I've noticed that in most examples (TSP and VRP), there is
        some separation between the model and the planning entity that
        is being moved around in the chain, which also makes sense. (For
        instance in TSP, Visit is the planning entity while City is the
        data entity). When the planning entity gets cloned, the data
        entity gets assigned to the clone.</div>
      <div><br>
      </div>
      <div>I am concerned however, that with my dependency between tasks
        and their end times (which are as such a property of the
        planning entity not the data entity) I won't be able to model
        them in this way. (For a task to know whether it has violated
        its hard constraint it needs to get access to the end time of
        its dependency, which is in the planning entity). My concern is
        that I might end up with a whole mess when it comes to the
        cloning of tasks. I am also concerned about the performance of
        computing the end time of each node recursively based on its
        previous task and dependent tasks.</div>
      <div><br>
      </div>
      <div>What is the best approach in this case?</div>
      <div><br>
      </div>
      <div>thanks,</div>
      <div><br>
        Josef</div>
      <div><br>
      </div>
      <div><br>
        <br>
        <div class="gmail_quote">On 25 July 2012 08:30, Geoffrey De Smet
          <span dir="ltr">&lt;<a moz-do-not-send="true"
              href="mailto:ge0ffrey.spam@gmail.com" target="_blank">ge0ffrey.spam@gmail.com</a>&gt;</span>
          wrote:<br>
          <blockquote class="gmail_quote" style="margin:0 0 0
            .8ex;border-left:1px #ccc solid;padding-left:1ex">
            <div bgcolor="#FFFFFF" text="#000000"> <br>
              <div>Op 24-07-12 23:14, Josef Bajada schreef:<br>
              </div>
              <blockquote type="cite">Hi Geoffrey,
                <div><br>
                </div>
                <div class="im">
                  <div>Thanks for your reply.</div>
                  <div><br>
                  </div>
                  <div>&gt; Does it make sense to wait longer than 7
                    mins after task A (presuming no other task forces
                    occupies the user at that time)?<br>
                    &gt; Put differently: Can we say that the starting
                    time of B = Math.max((endTime of task before B),
                    (endTime of task A + 7 minutes))?<br>
                    &gt; If we can say that, it's pointless to
                    investigate the solutions where task B starts 8
                    minutes after task A and the user doing no task that
                    last minute.<br>
                  </div>
                  <div><br>
                  </div>
                  <div>Yes, the starting time of B = Math.max((endTime
                    of task before B), (endTime of task A + 7mins)) as
                    long as it is smaller than (endTime of task A +
                    8mins).</div>
                  <div>Yes, it is pointless to investigate the solutions
                    where task B starts 8 minutes after task A and the
                    user doing no task that last minute.&nbsp;</div>
                  <div>The 8 minute is just a constraint that the task
                    in between tasks A and B cannot take longer than
                    7:59s.</div>
                  <div><br>
                  </div>
                  <div>I am thinking that maybe instead of using time
                    itself as the planning variable, we would use time
                    just to determine the Hard and Soft scores.&nbsp;</div>
                  <div>So if Task B is scheduled after Task A + 8mins by
                    the solver, then it inflicts on the hard score.
                    Similarly if Task B is scheduled before Task A + 7
                    mins.&nbsp;</div>
                  <div>Does my reasoning make sense in any way?</div>
                </div>
              </blockquote>
              Yes, but personally, I 'd design it differently (although
              I have no proof that my way would be better), like this:<br>
              "Task B is scheduled after Task A + 8mins by the solver"
              =&gt; make this a hard constraint<br>
              "Task B is scheduled before Task A + 7 mins" =&gt; make
              this a build-in hard constraint (= not a constraint in the
              scoreDRL or ScoreCalculator, but by design, see manual).<br>
              Each Task is assigned to a previousTaskOrPerson (and this
              variable is chained). It does not know it's startingTime
              directly.<br>
              The scoreDRL or ScoreCalculator calculates the
              startingTime of a Task dynamically, by applying this
              logic:<br>
              &nbsp; starting time of B = Math.max((endTime of
              previousTaskOrPerson of B), (endTime of task A + 7mins))<br>
              Note: "Chained=true" guarantees that there are no cycles
              of Tasks and that no Tasks exists with a
              previousTaskOrPerson == null.<br>
              Note: "(endTime of task A + 7mins)" is not hard coded in
              the score function: you won't find "7" or "A" in there.
              <div>
                <div class="h5"><br>
                  <br>
                  <blockquote type="cite">
                    <div><br>
                    </div>
                    <div>thanks,</div>
                    <div>Josef</div>
                    <div><br>
                    </div>
                    <div><br>
                      <br>
                      <div class="gmail_quote">On 24 July 2012 20:46,
                        Geoffrey De Smet <span dir="ltr">&lt;<a
                            moz-do-not-send="true"
                            href="mailto:ge0ffrey.spam@gmail.com"
                            target="_blank">ge0ffrey.spam@gmail.com</a>&gt;</span>
                        wrote:<br>
                        <blockquote class="gmail_quote" style="margin:0
                          0 0 .8ex;border-left:1px #ccc
                          solid;padding-left:1ex">
                          <div bgcolor="#FFFFFF" text="#000000"> <br>
                            <div>Op <a moz-do-not-send="true"
                                href="tel:23-07-12%2016"
                                value="+35623071216" target="_blank">23-07-12
                                16</a>:26, Josef Bajada schreef:<br>
                            </div>
                            <div>
                              <blockquote type="cite">Hi Geoffrey,
                                <div><br>
                                </div>
                                <div>Well I want to leave 'space'
                                  between tasks in the situations where
                                  there are hard constraints that
                                  require me to put this space.<br>
                                </div>
                              </blockquote>
                            </div>
                            This makes the chaining technique harder to
                            model, but I wouldn't write it off yet.
                            <div><br>
                              <blockquote type="cite">
                                <div><br>
                                </div>
                                <div>As a simple example:</div>
                                <div> <br>
                                </div>
                                <div>Task A: Put pasta in boiling water
                                  (duration 40 seconds)</div>
                                <div>Task B: Take pasta out of boiling
                                  water (duration 50 seconds, cannot
                                  start before 7 mins after Task A
                                  finishes, cannot start after 8 mins
                                  after Task A finishes)</div>
                              </blockquote>
                            </div>
                            Does it make sense to wait longer than 7
                            mins after task A (presuming no other task
                            forces occupies the user at that time)?<br>
                            Put differently: Can we say that the
                            starting time of B = Math.max((endTime of
                            task before B), (endTime of task A + 7
                            minutes))?<br>
                            If we can say that, it's pointless to
                            investigate the solutions where task B
                            starts 8 minutes after task A and the user
                            doing no task that last minute.<br>
                            If we can say that, then chaining can
                            calculate the the starting time of a task on
                            the fly differently.
                            <div><br>
                              <blockquote type="cite">
                                <div>Task C: Chop vegetables (duration 2
                                  minutes).</div>
                                <div><br>
                                </div>
                                <div>This will evidently leave some
                                  gaps. The ideal result from the solver
                                  should be:</div>
                                <div><br>
                                </div>
                                <div>Task A: at time 0 (ends at 40s)</div>
                                <div> Task C: at time 41s (ends at 2:41)</div>
                                <div>Task B: at time 7:40</div>
                                <div><br>
                                </div>
                                <div>There is a gap between C and B
                                  which is OK.&nbsp;</div>
                                <div><br>
                                </div>
                                <div>If another Task is added to the
                                  story:</div>
                                <div>
                                  <div>Task D: Prepare sauce (duration 7
                                    minutes)</div>
                                </div>
                                <div><br>
                                </div>
                                <div>I would want the following result:</div>
                                <div><br>
                                </div>
                                <div>Task A: at time 0 (ends at 40s)</div>
                                <div>Task D: at time 41s (ends 7:41s)</div>
                                <div>Task B: at time 8:42s (ends 9:32s)</div>
                                <div>Task C: at time 9:33s (ends 11:33s)</div>
                                <div><br>
                                </div>
                                <div>Task C can actually take place
                                  before Task A too.&nbsp;</div>
                                <div><br>
                                </div>
                                <div>I still need to read and understand
                                  the chaining functionality properly.
                                  Do you think it would allow me to
                                  achieve the above?</div>
                                <div><br>
                                </div>
                              </blockquote>
                            </div>
                            I don't know.<br>
                            But using continuous variables in a search
                            problem such as this that smells discrete
                            with discrete constraints (A must start
                            before B, ...), could blow up the search
                            space unnecessarily.<br>
                            <br>
                            If you want to look into using continuous
                            variables: the support for it is limited
                            currently.<br>
                            you can reuse the Drools Planner
                            metaheuristic algorithms (including
                            termination, score, ...), but there's no
                            decent generic move factory support for
                            continuous variables yet.<br>
                            So you 'll have to write a custom
                            MoveFactory that creates a limited subset of
                            moves.<br>
                            Also, construction heuristics can't handle
                            continuous variables yet, so you 'll have to
                            write a custom SolutionIntializer.<br>
                            There are examples with a custom MoveFactory
                            and a custom SolutionIntializer where you
                            can copy paste from, but none with
                            continuous variables at the moment.
                            <div>
                              <div><br>
                                <blockquote type="cite">
                                  <div>thanks,</div>
                                  <div><br>
                                  </div>
                                  <div>Josef</div>
                                  <div><br>
                                  </div>
                                  <div><br>
                                    <br>
                                    <div class="gmail_quote">On 22 July
                                      2012 20:05, Geoffrey De Smet <span
                                        dir="ltr">&lt;<a
                                          moz-do-not-send="true"
                                          href="mailto:ge0ffrey.spam@gmail.com"
                                          target="_blank">ge0ffrey.spam@gmail.com</a>&gt;</span>
                                      wrote:<br>
                                      <blockquote class="gmail_quote"
                                        style="margin:0 0 0
                                        .8ex;border-left:1px #ccc
                                        solid;padding-left:1ex">
                                        <div bgcolor="#FFFFFF"
                                          text="#000000"> Presuming that
                                          you don't want to leave space
                                          between tasks, you can design
                                          your model differently by
                                          using the "chained"
                                          functionality:<br>
                                          it will be far more efficient
                                          and the planning variable
                                          won't be continuous.<br>
                                          <br>
                                          Let's presume you're
                                          scheduling Tasks to Persons.<br>
                                          <br>
                                          @PlanningEntity<br>
                                          class Task implements
                                          TaskOrPerson {<br>
                                          <br>
                                          &nbsp;&nbsp;&nbsp; ...<br>
                                          <br>
                                          &nbsp;&nbsp;&nbsp; @PlanningVariable(chained
                                          = true)<br>
                                          &nbsp;&nbsp;&nbsp; @ValueRanges({<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; @ValueRange(type =
                                          ValueRangeType.FROM_SOLUTION_PROPERTY,

                                          solutionProperty =
                                          "taskList"),<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; @ValueRange(type =
                                          ValueRangeType.FROM_SOLUTION_PROPERTY,

                                          solutionProperty =
                                          "personList",<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;
                                          excludeUninitializedPlanningEntity
                                          = true)})<br>
                                          &nbsp;&nbsp;&nbsp; public TaskOrPerson
                                          getPreviousTaskOrPerson() {<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; return
                                          previousTaskOrPerson;<br>
                                          &nbsp;&nbsp;&nbsp; }<br>
                                          <br>
                                          &nbsp;&nbsp;&nbsp; public int getDuration() {<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; return duration;<br>
                                          &nbsp;&nbsp;&nbsp; }<br>
                                          <br>
                                          &nbsp;&nbsp;&nbsp; public int
                                          getStartingTime() {<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; int startingTime =
                                          0;<br>
                                          &nbsp;&nbsp;&nbsp; &nbsp;&nbsp;&nbsp; &nbsp; TaskOrPerson
                                          taskOrPerson =
                                          getPreviousTaskOrPerson();<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; while (taskOrPerson
                                          instanceof Task) { // Every
                                          chain is guarantee to end up
                                          with an anchor (= Person)<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; startingTime
                                          += ((Task)
                                          taskOrPerson).getDuration();<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; taskOrPerson =
                                          ((Task)
                                          taskOrPerson).getPreviousTaskOrPerson()<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; }<br>
                                          &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp; return startingTime;<br>
                                          &nbsp;&nbsp;&nbsp; }<br>
                                          <br>
                                          }<br>
                                          <br>
                                          class Person implements
                                          TaskOrPerson {<br>
                                          <br>
                                          }<br>
                                          <br>
                                          For a good example, take a
                                          look at the VehicleRouting
                                          example.<br>
                                          For more info about chaining,
                                          in the manual see section
                                          4.3.4.2.6. Chained<br>
                                          &nbsp; <a moz-do-not-send="true"
href="http://docs.jboss.org/drools/release/5.4.0.Final/drools-planner-docs/html_single/index.html"
                                            target="_blank">http://docs.jboss.org/drools/release/5.4.0.Final/drools-planner-docs/html_single/index.html</a><br>
                                          <br>
                                          <div>Op <a
                                              moz-do-not-send="true"
                                              href="tel:22-07-12%2018"
                                              value="+35622071218"
                                              target="_blank">22-07-12
                                              18</a>:00, Josef Bajada
                                            schreef:<br>
                                          </div>
                                          <blockquote type="cite">
                                            <div>
                                              <div>Hi,
                                                <div><br>
                                                </div>
                                                <div>I am new to Drools
                                                  and Drools Planner, so
                                                  apologies if I am
                                                  asking anything
                                                  obvious.</div>
                                                <div><br>
                                                </div>
                                                <div>My objective is to
                                                  implement a simple
                                                  (for now) planner
                                                  which schedules tasks
                                                  according to 2 main
                                                  criteria:</div>
                                                <div>- Their duration
                                                  (in seconds)</div>
                                                <div>- Their
                                                  dependencies on other
                                                  tasks (e.g. Hard
                                                  Constraint that Task B
                                                  has to start between
                                                  180 and 200 seconds
                                                  after Task A
                                                  finishes).</div>
                                                <div><br>
                                                </div>
                                                <div>Since there are
                                                  gaps between dependent
                                                  tasks as part of the
                                                  hard constraints other
                                                  tasks can be fitted in
                                                  between dependent
                                                  tasks.</div>
                                                <div>So the Solver needs
                                                  to find the optimal
                                                  start time for each
                                                  task that satisfies
                                                  the hard constraints,
                                                  and in the shortest
                                                  total timeline
                                                  possible to complete
                                                  all tasks (soft
                                                  constraint).</div>
                                                <div><br>
                                                </div>
                                                <div>The main problem I
                                                  am finding is that
                                                  this start time, which
                                                  is essentially the
                                                  planning variable is a
                                                  continuous variable.&nbsp;</div>
                                                <div>Chapter 4 of the
                                                  Drools documentation
                                                  mentions very briefly
                                                  (Section
                                                  4.3.4.1)&nbsp;&nbsp;that
                                                  planning variables can
                                                  be continuous, but
                                                  there does not seem to
                                                  be any more details
                                                  about how to achieve
                                                  this.</div>
                                                <div><br>
                                                </div>
                                                <div>Even if the
                                                  planning variable was
                                                  discrete (say bins of
                                                  5 second intervals),
                                                  there is no upper
                                                  bound as such.</div>
                                                <div><br>
                                                </div>
                                                <div>How is it best to
                                                  handle such planning
                                                  variables in Drools
                                                  Planner?</div>
                                                <div><br>
                                                </div>
                                                <div>thanks,<br>
                                                  josef</div>
                                                <div><br>
                                                </div>
                                                <div><br>
                                                </div>
                                                <br>
                                                <fieldset></fieldset>
                                                <br>
                                              </div>
                                            </div>
                                            <pre>_______________________________________________
rules-users mailing list
<a moz-do-not-send="true" href="mailto:rules-users@lists.jboss.org" target="_blank">rules-users@lists.jboss.org</a>
<a moz-do-not-send="true" href="https://lists.jboss.org/mailman/listinfo/rules-users" target="_blank">https://lists.jboss.org/mailman/listinfo/rules-users</a><span><font color="#888888">
</font></span></pre>
                                            <span><font color="#888888">
                                              </font></span></blockquote>
                                          <span><font color="#888888"> <br>
                                              <pre cols="72">-- 
With kind regards,
Geoffrey De Smet</pre>
                                            </font></span></div>
                                        <br>
_______________________________________________<br>
                                        rules-users mailing list<br>
                                        <a moz-do-not-send="true"
                                          href="mailto:rules-users@lists.jboss.org"
                                          target="_blank">rules-users@lists.jboss.org</a><br>
                                        <a moz-do-not-send="true"
                                          href="https://lists.jboss.org/mailman/listinfo/rules-users"
                                          target="_blank">https://lists.jboss.org/mailman/listinfo/rules-users</a><br>
                                        <br>
                                      </blockquote>
                                    </div>
                                    <br>
                                  </div>
                                  <br>
                                  <fieldset></fieldset>
                                  <br>
                                  <pre>_______________________________________________
rules-users mailing list
<a moz-do-not-send="true" href="mailto:rules-users@lists.jboss.org" target="_blank">rules-users@lists.jboss.org</a>
<a moz-do-not-send="true" href="https://lists.jboss.org/mailman/listinfo/rules-users" target="_blank">https://lists.jboss.org/mailman/listinfo/rules-users</a>
</pre>
                                </blockquote>
                                <br>
                                <pre cols="72">-- 
With kind regards,
Geoffrey De Smet</pre>
                              </div>
                            </div>
                          </div>
                          <br>
_______________________________________________<br>
                          rules-users mailing list<br>
                          <a moz-do-not-send="true"
                            href="mailto:rules-users@lists.jboss.org"
                            target="_blank">rules-users@lists.jboss.org</a><br>
                          <a moz-do-not-send="true"
                            href="https://lists.jboss.org/mailman/listinfo/rules-users"
                            target="_blank">https://lists.jboss.org/mailman/listinfo/rules-users</a><br>
                          <br>
                        </blockquote>
                      </div>
                      <br>
                    </div>
                    <br>
                    <fieldset></fieldset>
                    <br>
                    <pre>_______________________________________________
rules-users mailing list
<a moz-do-not-send="true" href="mailto:rules-users@lists.jboss.org" target="_blank">rules-users@lists.jboss.org</a>
<a moz-do-not-send="true" href="https://lists.jboss.org/mailman/listinfo/rules-users" target="_blank">https://lists.jboss.org/mailman/listinfo/rules-users</a>
</pre>
                  </blockquote>
                  <br>
                  <pre cols="72">-- 
With kind regards,
Geoffrey De Smet</pre>
                </div>
              </div>
            </div>
            <br>
            _______________________________________________<br>
            rules-users mailing list<br>
            <a moz-do-not-send="true"
              href="mailto:rules-users@lists.jboss.org">rules-users@lists.jboss.org</a><br>
            <a moz-do-not-send="true"
              href="https://lists.jboss.org/mailman/listinfo/rules-users"
              target="_blank">https://lists.jboss.org/mailman/listinfo/rules-users</a><br>
            <br>
          </blockquote>
        </div>
        <br>
      </div>
      <br>
      <fieldset class="mimeAttachmentHeader"></fieldset>
      <br>
      <pre wrap="">_______________________________________________
rules-users mailing list
<a class="moz-txt-link-abbreviated" href="mailto:rules-users@lists.jboss.org">rules-users@lists.jboss.org</a>
<a class="moz-txt-link-freetext" href="https://lists.jboss.org/mailman/listinfo/rules-users">https://lists.jboss.org/mailman/listinfo/rules-users</a>
</pre>
    </blockquote>
    <br>
    <pre class="moz-signature" cols="72">-- 
With kind regards,
Geoffrey De Smet</pre>