[wildfly-dev] Upcoming WF10 Dates (Reminder)

Jason Greene jason.greene at redhat.com
Thu Aug 13 15:48:38 EDT 2015


That’s correct, that’s my preference. The rationale is to limit the amount of component updates we have to bring in during the CR phase. Ideally if we are pulling in an update its to resolve an issue. 

> On Aug 13, 2015, at 1:33 PM, Heiko Braun <hbraun at redhat.com> wrote:
> 
> If I understand you correctly you want Final components for CR1?
> 
> /Heiko
> 
>> On 13 Aug 2015, at 19:42, Jason Greene <jason.greene at redhat.com> wrote:
>> 
>> Hello Everyone,
>> 
>> First off, I just wanted to say thank you everyone for hitting the major deliverables for the WF10 Beta release that went out over the weekend! 
>> 
>> The remaining schedule for WF10 is as follows:
>> 
>> WildFly 10 CR1              - September 9th  
>> WildFly 10 CR2 (if needed)  - September 16th 
>> WildFly 10 Final            - October 8th (contigent on certification)
>> 
>> So that means we have 26 days (17 workdays left) to:
>> 
>> - Stabilize features brought in during Alpha/Beta cycle
>> - Finish/polish compatibility (transformers, management ops, etc)
>> - Upgrade all components to Final (preferable) or CR (exceptional)
>> - Fix broken and/or intermittent tests relating to the above
>> - Address any other loose ends
>> 
>> We should avoid (if possible) introducing new major features to allow for enough time to do the above. Let me know ASAP if thats a problem.
>> 
>> Thanks!
>> 
>> --
>> Jason T. Greene
>> WildFly Lead / JBoss EAP Platform Architect
>> JBoss, a division of Red Hat
>> 
>> 
>> _______________________________________________
>> wildfly-dev mailing list
>> wildfly-dev at lists.jboss.org
>> https://lists.jboss.org/mailman/listinfo/wildfly-dev
> 

--
Jason T. Greene
WildFly Lead / JBoss EAP Platform Architect
JBoss, a division of Red Hat




More information about the wildfly-dev mailing list