JBoss Community

Re: Human task escalation understanding

created by javajbpmuser in jBPM - View the full discussion

Hi Maciej

thanks for the quick reply and for the help.

Actually I saw WS-HT specification, it says that after reassignment the task status changes from Reserved to ready and so the task could be claimed by on of the declared as potentiel owners or groups.But the limitation is when task is reassigned ,the only way to notify for that change is to send an e-mail.

In fact ,I would like to know if there any way to call a custom java service or method when the task is reassigned ( status changes from reserved to ready).that why I am asking if it is possible to catch the event that is responsible for changing task status after timeout.

 

Regards

Reply to this message by going to Community

Start a new discussion in jBPM at Community