Hi All,
I have the below requirement. And not able to find out the solution .
In process flow, I have two different navigationa to end the process .
1).End the process depending on the in put value and update the status in process params.
2). Create the Human tasks and update the status in same process params .
The initial params values while starting the process are stored in the audit logs. And able to retrieve.
The subsequent updated param value is not updated in the audit logs , Even though The same updated param value is available in
WorkflowProcessInstance instance.
Please help me , Thanks in Advance.
-Regards,
Lingaiah.S.