Hi,

There are 87 unresolved issues with Fix Version=4.2.1.Final (JBT) and 8.0.1.GA (JBDS) in our JIRA.
I believe we are not going to fix all of them in next 10 days:

https://issues.jboss.org/issues/?jql=project%20in%20(JBIDE%2C%20JBDS)%20AND%20resolution%20%3D%20Unresolved%20AND%20fixVersion%20in%20(4.2.1.Final%2C%208.0.1.GA)%20ORDER%20BY%20priority%20DESC

We are going to have one respin for 4.2.1.CR1 on 7th December ( + little one on 11th December if needed).

So, I'm asking all developers, please go to JIRA and mark all issues you are going to fix for 4.2.1/8.0.1 as:
Fix Version/s: 4.2.1.CR1 (or 8.0.1.CR for JBDS)
Label: respin-a

And make sure your QE are OK with your plans. The rest of the issues with fix version = "4.2.1.Final/8.0.1.GA" should be moved out to 4.2.2/8.0.2 or 4.2.x/8.0.x.

Thank you!