Hi Jeff, 

thanks for explanation.

Josef

On Tue, Jul 30, 2019 at 1:28 PM Jean-Francois Maury <jmaury@redhat.com> wrote:
Joseph,

the idea is to get the TP ready ASAP (so that we can fix broken builds) and you notice that the bits included into this TP are ready from September 18
 so that the TP will not be build in one day

On Tue, Jul 30, 2019 at 8:42 AM Josef Kopriva <jkopriva@redhat.com> wrote:
Hi Jeff, 

I would just add sign-off dates for QE:
24-Sep-2019 - 4.13.0.AM1 QE sign-off
8-Oct-2019 - 4.13.0.Final QE sign-off

And I have a question regarding Final TP freeze: is it enough one day for TP update? AM1 release is scheduled for 24-Sep-2019 and the next day is Final TP freeze. Usually Final TP freeze is one day before Final freeze - in this release it would be 2-Oct-2019.

Thanks.
Josef

On Mon, Jul 29, 2019 at 11:08 PM Jean-Francois Maury <jmaury@redhat.com> wrote:
Hello,

please find the proposed schedule dates for JBoss Tools and CodeReady Studio based on Eclipse 2019-09

Upstream:
2019-09.M119-Jul-2019
2019-09.M2 9-Aug-2019
2019-06.M3 30-Aug-2019
2019-09.RC1 6-Sep-2019
2019-09.RC2 13-Sep-2019
2019-09 GA 18-Sep-2019

Sprints:
12-Jun-20192-Jul-2019168Nymphea
3-Jul-201923-Jul-2019169
24-Jul-201913-Aug-2019170
14-Aug-20193-Sep-2019171
4-Sep-201924-Sep-2019172Orchid
25-Sep-201915-Oct-2019173

Dependencies
EAP CD 17 GA25-Jul-2019
EAP 7.3 Beta26-Aug-2019
Wildfly 18 Beta4-Sep-2019
Wildfly 1819-Sep-2019
EAP CD 18 GA12-Nov-2019
EAP 7.3 GA21-Jan-2020

So, in chronological order:
devex #1682-Jul-2019
2019-09.M119-Jul-2019
devex #16923-Jul-2019
EAP CD 17 GA25-Jul-2019
2019-09.M2 9-Aug-2019
devex #17013-Aug-2019
EAP 7.3 Beta26-Aug-2019
2019-06.M3 30-Aug-2019
devex #1713-Sep-2019
Wildfly 18 Beta4-Sep-2019
2019-09.RC1 6-Sep-2019
2019-09.RC2 13-Sep-2019
2019-09 GA 18-Sep-2019
Wildfly 1819-Sep-2019
devex #17224-Sep-2019
devex #17315-Oct-2019

So, the proposed schedule could be the following:

17-Sep-2019
4.13.0.AM1 TP Code Freeze (based on 2019-09.RC1)
18-Sep-2019
4.13.0.AM1 Code Freeze
20-Sep-2019
4.13.0.AM1 staged for QE
24-Sep-2019
4.13.0.AM1 released
25-Sep-2019
4.13.0.Final TP Code Freeze (based on 2019-09 GA)
2-Oct-2019
4.13.0.Final Code Freeze
4-Oct-2019
4.13.0.Final staged for QE
11-Oct-2019
12.13.0.GA pushed to stage by RCM
14-Oct-2019
12.13.0.GA pushed to prod by RCM
15-Oct-2019
12.13.0.GA announced

So, the bits will be based on 2019-09 and will support Wildfly 18 and EAP 7.3 Beta (Tech Preview)
WDYT ?
--

Jeff Maury

Manager, DevTools

Red Hat EMEA

jmaury@redhat.com   



--

Josef Kopriva

Quality Engineer

Red Hat

Purkynova 111

612 00 Brno    IM: jkopriva



--

Jeff Maury

Manager, DevTools

Red Hat EMEA

jmaury@redhat.com   



--

Josef Kopriva

Quality Engineer

Red Hat

Purkynova 111

612 00 Brno    IM: jkopriva