https://issues.jboss.org/browse/RTGOV-380?focusedWorklogId=12431196&p...
]
Gary Brown logged work on RTGOV-380:
------------------------------------
Author: Gary Brown
Created on: 07/May/14 7:04 AM
Start Date: 07/May/14 7:04 AM
Worklog Time Spent: 4 days
Issue Time Tracking
-------------------
Remaining Estimate: 2 days (was: 1 week, 1 day)
Time Spent: 1 week, 3 days (was: 4 days)
Worklog Id: (was: 12431196)
Support RTGov UI in Karaf
-------------------------
Key: RTGOV-380
URL:
https://issues.jboss.org/browse/RTGOV-380
Project: RTGov (Run Time Governance)
Issue Type: Sub-task
Reporter: Gary Brown
Assignee: Gary Brown
Fix For: 2.0.0.Final
Original Estimate: 2 weeks
Time Spent: 1 week, 3 days
Remaining Estimate: 2 days
Enable the new RTGov UI war to be deployed in Karaf.
--