We're aiming to have WildFly 35.0.0.Final available on wildfly.org on Thursday, January 9. The beta should be available on December 12.

Following are the key dates:

Wed Dec 4 -- Feature Freeze. Mergeable feature PRs due
Mon Dec 9 -- WF Core Beta release
Wed Dec 11 -- Tag/deploy 35 Beta
Thu Dec 12 -- Announce release

Wed Dec 18 -- Mergeable Final PRs due

Thu Jan 2 -- Last minute PRs for Final due
Mon Jan 6 -- WF Core Final release
Wed Jan 8 -- Tag/deploy 35 Final
Thu Jan 9 -- Release available on wildfly.org
Fri Jan 10 -- Post release deliverables

As usual, there is a longer period between the beta and the final for the January release. This results in two deadlines for PRs for the final. The Dec 18 date is the normal date, two weeks after the feature freeze. That's the deadline everyone should work toward. 

Then there's a Jan 2 date to pick up fixes for any critical issues that popped up after Dec 18.

Best regards,

--
Brian Stansberry
Principal Architect, Red Hat JBoss EAP
WildFly Project Lead
He/Him/His