A) RFEs
We decided this could come in a post-GA update, so it's Green. I've been working on tests.
B) Critical / Blocker bugs
4) Publicity
5) Other
4 day holiday weekend
More on publishing rendered quickstart content via GitHib Pages.
Wrote a test plan for WildFly Galleon Plugins project.
Discussed/published a dev schedule for WF 31. Moved the planned date for the beta to Dec 21.
Review/merge of Paul's port of extension/subsystem development APIs from full WF to WF Core.
5) Next Steps
Testing of EAP7-2151 and channel provisioning
Work to get Paul Ferraro's stability level work merged.
I may be asked to present re the LGPL->ASL transition on next week's MW eng all hands call.
EAP 8 / XP 5 as needed
WildFly 31 beta preparation
More on layers testing improvements; seems I missed something
Move my mvc-krazo feature pack to wildfly-extras and perhaps integrate into WF Preview 31 Beta