WildFly 31 is getting close, so here are the dates we are looking at for the release activities. Note that these are a week later than some preliminary estimates, so be sure and read these!

31 Beta

Wed Dec 13 -- PR submission deadline
Fri Dec 15 -- WildFly Core ready to tag
Mon Dec 18 -- Final merges and checks
Tue Dec 19 -- Buffer day
Wed Dec 20 -- Tag and deploy to repository.jboss.org
Thu Dec 21 -- Release available on wildfly.org, public announcement.
Fri Dec 22 -- Other release deliverables not ready on release day.


31 Final (tentative)

Wed Jan 10 -- PR submission deadline
Fri Jan 12 -- WildFly Core ready to tag
Mon Jan 15 -- Final merges and checks
Tue Jan 16 -- Buffer day
Wed Jan 17 -- Tag and deploy to repository.jboss.org
Thu Jan 18 -- Release available on wildfly.org, public announcement.
Fri Jan 19 -- Other release deliverables not ready on release day.

As is usual for our January releases, the gap between the beta and final is longer than usual.

Note that the dates for WildFly 31 Final are still tentative. There's been some consideration of extending it an additional week to give time to prepare some promotional activities around the release.

Best regards,

--
Brian Stansberry
Principal Architect, Red Hat JBoss EAP
WildFly Project Lead
He/Him/His