FYI, following is the development schedule for WildFly 32. We're aiming to continue with our pattern of 4 feature releases per year, with Final generally coming in January, April, July, October.

WF 32 Beta

Feature freeze -- Wed Mar 20
WF Core release -- Mon Mar 25
Server Tag -- Wed Mar 27
Available on wildfly.org + ancillary deliverables -- Thu Mar 28

WF 32 Final

Code freeze -- Wed Apr 3
WF Core release, complete merging -- Mon Apr 8
Server tag -- Wed Apr 10
Available on wildfly.org + ancillary deliverables -- Thu Apr 11
Misc deliverables not doable by Apr 11 -- Fri Apr 12


Best regards,

--
Brian Stansberry
Principal Architect, Red Hat JBoss EAP
WildFly Project Lead