[aerogear-dev] [UnifiedPush Server] release timelines
Matthias Wessendorf
matzew at apache.org
Tue Aug 5 08:00:55 EDT 2014
There might be a little delay, when we can release our own 1.0.0.Final,
since I found a KC bug that occurs only w/ MySQL and EAP 6.3.Beta:
http://lists.jboss.org/pipermail/keycloak-dev/2014-August/002388.html
In case this fix makes it into Keycloak's RC-1 (instead of beta-4 - which
seems reasonable to me), we should be waiting a few more days to pick up
their RC-1 in our final. That means we could release the same week (e.g.
22nd), or exactly one week later - on 25th of August.
Things are being discussed atm, this is just a heads-up ...
-Matthias
On Fri, Aug 1, 2014 at 3:19 PM, Matthias Wessendorf <matzew at apache.org>
wrote:
> here we go:
>
> https://github.com/aerogear/aerogear.org/pull/343
>
>
> On Fri, Aug 1, 2014 at 2:47 PM, Lucas Holmquist <lholmqui at redhat.com>
> wrote:
>
>> ++ sounds/looks good
>> On Aug 1, 2014, at 12:35 AM, Matthias Wessendorf <matzew at apache.org>
>> wrote:
>>
>> Hi team,
>>
>> based on [1] I thought about our release timelines until 1.0.0.Final, and
>> shortly after.
>>
>> -
>>
>> 1.0.0.Beta2
>> <https://issues.jboss.org/browse/AGPUSH/fixforversion/12325092/?selectedTab=com.atlassian.jira.jira-projects-plugin:version-issues-panel>:
>> 07/Aug/14
>>
>> This needs to include Keycloak-beta4, and might slip by one day, but not
>> much more of a delay.
>>
>> *Please note:* There is already works going on to have our parent and
>> UPS working w/ beta4 - it’s just a matter of merging the branch, once the
>> release is out.
>>
>> Number of open JIRAs for this release is looking good!
>>
>> -
>>
>> 1.0.0
>> <https://issues.jboss.org/browse/AGPUSH/fixforversion/12323754/?selectedTab=com.atlassian.jira.jira-projects-plugin:version-issues-panel>:
>> 18/Aug/14
>>
>> *Keycloak:* This will use keycloak’s beta4 as well, unless we find
>> BLOCKERS in their beta4... (As said before KC is mostly hidden inside the
>> server, and we can not wait for their 1.0.0.Final in September)
>>
>> This release will be mostly around docs and perhaps some more UX review
>> of the quickstart demos. It is possible that the UX review does not happen.
>>
>> *CODE FREEZE:* I’d suggest we do a *code freeze* for the UnifiedPush
>> Server on 11/Aug/14. This is pretty much shortly after the beta2 and gives
>> us one week of deep testing (of server, docs, demos) before the final
>> release.
>>
>> Next: *celebrate*!!!!!!!! [image: :tada:]
>>
>> After the 1.0.0.Final of UPS, I’d suggest a two week-based release series
>> of small fixes and improvements, as well as taking up new Keycloak releases
>>
>> -
>>
>> 1.0.1
>> <https://issues.jboss.org/browse/AGPUSH/fixforversion/12325080/?selectedTab=com.atlassian.jira.jira-projects-plugin:version-issues-panel>:
>> 01/Sep/14
>>
>> *Keycloak:* main reason is pick-up of their 1.0-RC-1 and those few items
>> from the JIRA.
>>
>> -
>>
>> 1.0.2
>> <https://issues.jboss.org/browse/AGPUSH/fixforversion/12325081/?selectedTab=com.atlassian.jira.jira-projects-plugin:version-issues-panel>:
>> 15/Sep/14
>>
>> *Keycloak:* main reason is pick-up of their 1.0.0.Final
>>
>> -
>>
>> 1.0.3
>> <https://issues.jboss.org/browse/AGPUSH/fixforversion/12325082/?selectedTab=com.atlassian.jira.jira-projects-plugin:version-issues-panel>
>> :29/Sep/14
>>
>> Might not be needed - but added it to JIRA, just in case…
>>
>> Let me know your thoughts and I will update the roadmap!
>>
>> -Matthias
>>
>> [1] http://lists.jboss.org/pipermail/keycloak-dev/2014-July/002360.html
>>
>> --
>> Matthias Wessendorf
>>
>> blog: http://matthiaswessendorf.wordpress.com/
>> sessions: http://www.slideshare.net/mwessendorf
>> twitter: http://twitter.com/mwessendorf
>> _______________________________________________
>> aerogear-dev mailing list
>> aerogear-dev at lists.jboss.org
>> https://lists.jboss.org/mailman/listinfo/aerogear-dev
>>
>>
>>
>> _______________________________________________
>> aerogear-dev mailing list
>> aerogear-dev at lists.jboss.org
>> https://lists.jboss.org/mailman/listinfo/aerogear-dev
>>
>
>
>
> --
> Matthias Wessendorf
>
> blog: http://matthiaswessendorf.wordpress.com/
> sessions: http://www.slideshare.net/mwessendorf
> twitter: http://twitter.com/mwessendorf
>
--
Matthias Wessendorf
blog: http://matthiaswessendorf.wordpress.com/
sessions: http://www.slideshare.net/mwessendorf
twitter: http://twitter.com/mwessendorf
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.jboss.org/pipermail/aerogear-dev/attachments/20140805/5f7610a8/attachment-0001.html
More information about the aerogear-dev
mailing list