[hibernate-dev] [HV] Release plan for a version compatible with Bean Validation 1.1.0.Alpha1
Gunnar Morling
gunnar.morling at googlemail.com
Mon Mar 26 16:27:06 EDT 2012
Hi,
sorry for the late response.
I think we might start with the work on HV 5 as soon as we got HV
4.3.0.CR1 released. Ideally then we shouldn't have any further changes
for 4.3.0.Final, or in the bad case it should be minor bugfixes only,
which should allow us to rebase the HV 5 branch on that without too
much effort.
This would also give us a bit more time to gather user feedback on the
4.3.0 CR (or release another CR) without having to rush the release in
order to get started with the 5.0 development.
Once we've started, I think we could have 5.0.0.Alpha1 out within 3 or
4 weeks, so this would be ~6 weeks from now. Of course this depends on
how much time we can put into this, but this should be doable given
the current velocity we have.
Does that sound reasonable?
--Gunnar
2012/3/23 Hardy Ferentschik <hardy at hibernate.org>:
>
>>> That's also my preference. Let's get out a strictly backwards-compatible HV 4.3 asap, and then proceed with HV 5 as first release based on BV 1.1. I'm not sure though, whether we'll have a first Alpha ready within one month, given that we have to finalize 4.3 before.
>>>
>> So when?
>
> We heavily prioritized the remaining 4.3 issues and there are only 11 left now. I am working on getting most of them sorted out by next week were we
> are planning Beta1. CR and Final will follow closely. Let's say three weeks for 4.3 Final.
>
> I am not sure atm how much work it will be to align the current method level validation with the spec. Gunnar is probably in a better position to give an
> estimate for that.
>
> --Hardy
>
>
> _______________________________________________
> hibernate-dev mailing list
> hibernate-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/hibernate-dev
More information about the hibernate-dev
mailing list