[infinispan-dev] Update on next release date (5.2.0.Alpha3)
Manik Surtani
manik at jboss.org
Fri Aug 3 08:28:51 EDT 2012
Awesome. Do you have a plan for some early stress testing of this? Maybe see if Martin or Erik is willing to help here?
On 3 Aug 2012, at 12:31, Mircea Markus wrote:
> Hi,
>
> The main goal of the next Alpha release is getting NBST(ISPN-1424) out (alpha-stable). After discussing with Dan and Adrian, here's the action plan:
> - Dan/Adrian will issue a pull request Mon/Tue (6-7 Aug)
> - given the complexity of the change, the review for this is expected to take up to a week. During this time, besides answering review comments, they will consolidate the implementation
> - finally the release is estimated to happen at the beginning of the week starting 13 August - the day to be confirmed later on next week
>
> Thanks,
> Mircea
> _______________________________________________
> infinispan-dev mailing list
> infinispan-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/infinispan-dev
--
Manik Surtani
manik at jboss.org
twitter.com/maniksurtani
Founder and Project Lead, Infinispan
http://www.infinispan.org
Platform Architect, JBoss Data Grid
http://red.ht/data-grid
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.jboss.org/pipermail/infinispan-dev/attachments/20120803/dc818d47/attachment.html
More information about the infinispan-dev
mailing list