>> The main goal of the next Alpha release is getting NBST(ISPN-1424) out (alpha-stable). After discussing with Dan and Adrian, here's the action plan:
>> - Dan/Adrian will issue a pull request Mon/Tue (6-7 Aug)
>> - given the complexity of the change, the review for this is expected to take up to a week. During this time, besides answering review comments, they will consolidate the implementation
>> - finally the release is estimated to happen at the beginning of the week starting 13 August - the day to be confirmed later on next week
>>
>> Thanks,
>> Mircea
>> _______________________________________________
>> infinispan-dev mailing list
>> infinispan-dev at lists.jboss.org
>> https://lists.jboss.org/mailman/listinfo/infinispan-dev
> Mircea, I've got ISPN-1978 (allow modules to extend the configuration
> schema) nearly ready to go, but I need some extra testing. I'll try and
> get it done by the Mon/Tue as well.
Perfect, thanks!