I'm missing the upgrade to JGroups 3.2.5 in the list :-(

I also suggest moving the release data to Dec 22: then you don't have to 
do the release as the 21st is the end of the world ha ha :-)

On 12/18/12 7:31 PM, Mircea Markus wrote:
> Hi,
>
> Next Infinispan release(5.2.0.CR1) is scheduled for Friday 21 Dec.
> We still have 19 issues (blocker + critical) that must make it in for 
> CR[1]. Besides this we are still waiting for input from QA - hopefully 
> things will stabilise at this stage.
> Realistically speaking we won't be able to solve all 19 issues this 
> the end week of this week, so I've moved the release date to  Jan 4th 
> (Friday).
> Also please review the JIRAs[1] assigned to you and approach the 
> blocker/critical JIRAs first.
>
> [1] http://goo.gl/iV9MQ
>
> Cheers,
> -- 
> Mircea Markus
> Infinispan lead (www.infinispan.org <http://www.infinispan.org>)
>
>
> _______________________________________________
> infinispan-dev mailing list
> infinispan-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/infinispan-dev

-- 
Bela Ban, JGroups lead (http://www.jgroups.org)



More information about the infinispan-dev mailing list