Hi all,
I have updated Jira with the next milestones for 9.1.0
9.1.0.CR1 - 30th June
9.1.0.Final - 14th July
This extends the traditional minor-release timebox by two weeks,
essential because the features we wanted for Beta were a bit late.
From now until the end we should only consider features whose PR have
been open for a while (e.g. scattered cache). Bug fixes and minor
enhancements to existing features are obviously allowed.
Anything else will need to be shunted to 9.2.0.
Tristan
--