[jboss-dev-forums] [Design of JBoss jBPM] - Re: ending a process from other token than root token

kukeltje do-not-reply at jboss.com
Mon Jun 2 08:45:25 EDT 2008


anonymous wrote : I would guess that a majority assumes the rest of the process will not be cancelled. 
  | 
Well, then the two of my collegues that used jBPM and myself belong to a minority (which bny itself is cool, since I hate being part of a majority)

anonymous wrote :  there is some logic that each time a token ends, it checks if there is some parent token still active.
Correct, that is the behaviour, which would not be a real problem if there also was e.g. the option to cancel certain tokens/tasks with a tag in e.g. the end node, or in many other places. BPMN has some notion/notation for this.


View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4155025#4155025

Reply to the post : http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&p=4155025



More information about the jboss-dev-forums mailing list