Don't schedule things for GA.
Everything should be done by CR1 (especially api changes).
In principle GA could/should just be
svn copy micrcontainer/tags/2.0.0.CR1 microcontainer/tags/2.0.0.GA
(it can't actually be that because the poms have to be updated with the version :-)
That doesn't mean we can't do fixes in the GA, it just means we shouldn't be
expecting to do so until after the first CR1 is released.