The team are starting to look at the next project release of the ESB 4.x stream and will shortly begin development in earnest.

The proposed schedule is as follows

Requirements and new functionality
  now - 28th November

  Discuss requirements and select development tasks that are to be included in the next project release.  This will primarily focus on feature requests and improvements to current capabilities.

Development
  1st December - 30th January

  Main development tasks will progress, except for holiday period and f2f meeting.  During this phase we will accept additional bug fix requests but most feature requests will be postponed to the next release.

Testing
  February 2nd - February 13th

  Testing of the codebase with critical bug fixes being accepted.

Release
  February 13th.

If you have any suggestions for new functionality, or enhancements to the current codebase, then please let us know about them by creating a JIRA request and setting the 'fix version' to '4.5 feature requests'.

Thanks,

ESB team

View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4189363#4189363

Reply to the post : http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&p=4189363



More information about the jboss-dev-forums mailing list