[jboss-dev-forums] [Design of JBoss jBPM] - Re: [BPMN2] How to implement uncontrolled sequence flow beha
kukeltje
do-not-reply at jboss.com
Thu Jul 30 07:41:05 EDT 2009
"tom.baeyens at jboss.com" wrote : the real solution is to implement it in the BPMN activity base class.
|
| add a method to the BpmnActivity like leaveBpmnActivity(ExecutionImpl execution)
|
I'll do that. Filed https://jira.jboss.org/jira/browse/JBPM-2458
"tom.baeyens at jboss.com" wrote :
| (ps you already might have noticed that in our own implementations, it is best to use the impl classes and not the interfaces)
The impl of the pvm? Hmm... missed that, maybe because Bernd already did some work before me.
View the original post : http://www.jboss.org/index.html?module=bb&op=viewtopic&p=4246951#4246951
Reply to the post : http://www.jboss.org/index.html?module=bb&op=posting&mode=reply&p=4246951
More information about the jboss-dev-forums
mailing list