This is indeed what I used something similar for in jBPM 3. It's not that difficult since you can retrieve the processdefinition in xml as a resource from the deployment and use xpath on it for retrieving the additional attributes.
What I did (amongs other things) was adding an attribute to a task with the average duration (different from the duedate). Without extending the database, I was able to use this.
Otoh, in jBPM 4 it is much easier to extend an activity then it was in jBPM 3 since there is no database model to be extended. Just extend the activity and change the activities xml config file and you are done. The two solutions can coexist without any problem, although I think the activities config file was more for new node types than extending existing ones.
View the original post : http://www.jboss.org/index.html?module=bb&op=viewtopic&p=4258982#4258982
Reply to the post : http://www.jboss.org/index.html?module=bb&op=posting&mode=reply&p=4258982
More information about the jboss-dev-forums
mailing list