Jason T. Greene wrote:
> Hi Guys,
>
> Now that M1 is out lets talk about M2 and what can make the release. The 
> tentative release plan we have talked about is a integration freeze on 
> Feb 1, with an eventual freeze in late Feb. However, before we get more 
> absolute dates we really need to nail down on what we aim to deliver in 
> that time frame.
>
>  From an EE perspective it seems the following are close enough that 
> they could make such a schedule:
>
> Full Servlet 3
> Full JPA 2
> Some EJB 3.1 capabilities (but which ones?)
>   
1) no-interface view for EJBs
2) Support for deployment of EJBs in .war files (Carlo has been working 
on this)