[jboss-dev] Re: AS 5.1 Component Project Schedule

Alexey Loubyansky alexey.loubyansky at redhat.com
Thu Feb 5 02:19:36 EST 2009


Metadata 1.0.0.GA
XB 2.0.1 GA (or CR, there is no roadmap and development is done mostly 
on demand)

Jason T. Greene wrote:
> Project Leads,
> 
> The next planned AS release is 5.1 Beta which we are targeting for a 
> March release, and a following GA in April (provided no major problems).
> 
> I need to know what versions of your respective components you would 
> like included in this release. These would preferably be of CR or better 
> quality, although a beta release may be OK if you are confident you can 
> get a GA shortly thereafter. It would also be helpful if you could limit 
> the scope of whatever version you are targeting for AS inclusion to be 
> the features that benefit AS.
> 
> Keep in mind that we are transitioning to a frequent release cycle for 
> the AS, so there is no need to rush your project to make this release. 
> The more stable the project releases are, the less time it takes getting 
> the AS ready to release.
> 
> Thanks!
> 



More information about the jboss-development mailing list