[jboss-dev] Finalized AS 5.1 Schedule

Dimitris Andreadis dandread at redhat.com
Tue Mar 3 03:04:47 EST 2009


It's not planned, but you never know.

Richard Opalka wrote:
> Hi,
> 
>   little bit out of topic but is JBossAS 5.0.2 release planned?
> I'm asking because we need to decide  whether AS Branch_5_0
> should be included in our QA hudson matrix or not.
> 
> Cheers,
> 
> Richard
> 
> Jason T. Greene wrote:
>> The AS 5.1 community schedule has been updated to account for the 
>> embedded console time-line. Essentially an additional month was added 
>> to the CR1 phase. The new dates are as follows:
>>
>> 5.1 Beta1 (Same)
>> ---------
>> Primary Goal: Completion of profile service work necessary for the 
>> console
>> Secondary Goal: Introduction of New Components (Web Beans Preview, JDK 
>> Logging, JBoss Threads, Bootstrap) & Misc Updates (EJB3, JPA, 
>> security, clustering, Web Services)
>>
>> Code Freeze: March 9th
>> Release:     March 16th
>>
>> 5.1 CR1 (Shifted)
>> -------
>> Primary Goal: Inclusion of a working console for community testing
>> Secondary Goal: Inclusion of JBM2 tech preview
>>
>> Code Freeze: May 12th
>> Release:     May 19th
>>
>> 5.1 GA (Shifted)
>> -------
>> Primary Goal: Shipping the first release with a real admin console
>>
>> Code Freeze: June 8th
>> Release:     June 15th
>>
> 
> 