[jboss-dev] Accelerated 5.1 Timeline (New Dates!)
Max Rydahl Andersen
max.andersen at redhat.com
Wed Mar 18 09:51:25 EDT 2009
> I guess, now!
We won't be around much before after eclipsecon ;(
But lets get it started at least.
Any way to get a "restfull"/non-binary-dependent API to a running
appserver/profileservice ?
or is there a client only api/jar set for profileservice that won't
change or at least be backward compatible going forward
so tooling won't break when a new AS or EAP release comes out ?
Any way for the profileservice to provide deployment-local
exception/error/debug info ?
/max
>
> Max Rydahl Andersen wrote:
>>
>> At what phase/time-period would tools requirements be discussed ?
>>
>> Last time we said early april but with this schedule is there any
>> room for that ?
>>
>> /max
>>> Due to recent changes in the EAP5 schedule, we have had to
>>> significantly pull in our community dates. The new CR1 and GA dates
>>> are as follows:
>>>
>>> CR1
>>> ---
>>> Code/Component Freeze : April 20th
>>> Final Console Inclusion : April 22nd
>>> Release : April 27th
>>>
>>> GA
>>> --
>>> Code/Component Freeze : May 11th
>>> Release : May 25th
>>>
>>>
>>> There is now only 1 goal, and that is meeting our dates with a
>>> working console.
>>>
>>> This also means profile service work is the priority:
>>> https://jira.jboss.org/jira/browse/JBAS-6620
>>>
>>> All other updates are a nice to have, and if you want them included
>>> in 5.1, they need to be done as early as possible.
>>>
>>
>> _______________________________________________
>> jboss-development mailing list
>> jboss-development at lists.jboss.org
>> https://lists.jboss.org/mailman/listinfo/jboss-development
> _______________________________________________
> jboss-development mailing list
> jboss-development at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/jboss-development
More information about the jboss-development
mailing list