I think we can get the operational logging stuff together too - it's a
relatively small item, and it's mainly a question of getting the
requirements settled and we seem to be trucking along on this.
- DML
On 02/18/2010 10:03 AM, Jason T. Greene wrote:
> Hello everyone,
>
> Thanks again for all the hard work on M2. Now that it's out the door,
> it's time to look at our plan/goals for M3.
>
> The tentative code/component freeze date for M3 is March 22. Please let
> me know what updates you feel comfortable including in this release.
>
> Ideally we would be able to deliver:
> - Completed HornetQ Integration
> - Remoting 3 Integration
> - Various major EJB 3.1 features
>
> Let me know your thoughts on this.
>