Jason T. Greene wrote:
> Hi Guys,
>
> Now that M1 is out lets talk about M2 and what can make the release. The
> tentative release plan we have talked about is a integration freeze on
> Feb 1, with an eventual freeze in late Feb. However, before we get more
> absolute dates we really need to nail down on what we aim to deliver in
> that time frame.
>
> From an EE perspective it seems the following are close enough that
> they could make such a schedule:
>
> Full Servlet 3
> Full JPA 2
> Some EJB 3.1 capabilities (but which ones?)
>
I'll have most JAX-RS integration. Full integration (and spec required)
can't happen without MC/EJB changes. I need scanning features and field
injection SPIs.
I'll have initial commit in by Feb 1st.
--