"kukeltje" wrote : the latter, see my previous posts. If you take that into account isn't the task-assign event very clear? ;-)
Yes, indeed. VERY clear ;-)
I am also in favour of the idea that the engine should have a seperate event for group-assignment. However, the differentiation in "task-assign"-event firing between an assignment being done in a task and being done in a swimlane is probably a bug.
I created two junit-tests and a Jira issue for this:
http://jira.jboss.com/jira/browse/JBPM-1032
View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4070154#4070154