In a process definition which has a sub process, how is the control passed on from the super process instance to the sub processes. Also when the sub processes execution is complete how is the control passed on back to the super process?
I'm using 3.2GA version and have added the logic for changing the token to the respective process instance's token as and when the control moves from 1 process to another.
Is this how it should be normally done?
Thanks in Advance,
Shridevi