[jboss-user] [JBoss jBPM] - Re: please help: concurrent paths execution

ax666 do-not-reply at jboss.com
Wed May 30 10:49:00 EDT 2007


I could synchronize in JobExecutorThread on the parent token, but that hack seems even dirtier than the other. I'll give it a try though ;)

What did everyone else do in case of concurrent threads in a process instance? the discussions I found in the forum never came to a conclusion...

I'm leaving the jira issue as is for now...

View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4049752#4049752

Reply to the post : http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&p=4049752



More information about the jboss-user mailing list