[jboss-user] [JBoss jBPM] - Re: Synchronising tasks finish-to-finish

pojomonkey do-not-reply at jboss.com
Fri Feb 29 05:31:16 EST 2008


I tried putting a condition on a leaving transition - but that just complicates matters.

"kukeltje" wrote : Why not simply introduce things like 'prepare shipment' that is where the ship item is now and move the ship item below the join....
Interesting thought - I could have a 'start' even before the join(s) and a 'stop' even after the join...

In which case I'll just want an 'event' node - sounds like a 'vanilla' node with an action...

Thanks for the inspiration :)

View the original post : http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4133142#4133142

Reply to the post : http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&p=4133142



More information about the jboss-user mailing list