[jboss-user] [JBoss jBPM] - modelling worklows with parallel nodes
AJanz
do-not-reply at jboss.com
Sun Mar 9 18:35:33 EDT 2008
i got to model the following workflow
i got a start node
from start node, i want to notify three different departments to do some work. the work of the three departments should be done at the same time, when all three they got their work done, the workflow will go to an end node with a final proof. a simple workflow i think
how can i model this using jbpm?
thanks
sascha