[jboss-user] [jBPM Users] - Form Validation

dmigowski do-not-reply at jboss.com
Fri Nov 20 04:38:17 EST 2009


Hello dear jBPM users,

how do you realize Form validation? Currently the only option i see is to let a decision node follow the task node, and if there was a problem with the entered data, to go back to the task.

This however has the disadvantage that timers are resetted. To stop them from being resetted, i would have to add a parallel flow with a wait state which a trigger by event, when the form is successfully completed.

Do i do it right?

Thanks in advance,
Daniel Migowski

View the original post : http://www.jboss.org/index.html?module=bb&op=viewtopic&p=4266701#4266701

Reply to the post : http://www.jboss.org/index.html?module=bb&op=posting&mode=reply&p=4266701



More information about the jboss-user mailing list