Hi,
About transitions, In websale example,
"Evaluate web order" task node have two transitions, one is "OK" and another one is "More info needed" but whenever we selecting "More info needed" it still follows with "OK". Why? 

I m using 3.2.2, I changed the order of transition in source code of processdefinition.xml, then it is taking the path of the first transition, its not behaving as according to the transition name. It is just responding to one transition. I saw the jira, but not got the correct path.

If anybody solved this type of error then let me know. 