Hi,
thanks for the example

is it possible to base the escalation on a timer or a time event
the example uses message events

what i'm looking for is the the following
the process reaches a user task, but the user does not complete the task
i want to set a time escalation on the user task so that if for the example the user hasn't completed the
task in a day we can send the user a mail reminder to complete the task ?
--------------------------------------------------------------

Reply to this message by going to Community
[http://community.jboss.org/message/595098#595098]

Start a new discussion in jBPM at Community
[http://community.jboss.org/choose-container!input.jspa?contentType=1&containerType=14&container=2034]

-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.jboss.org/pipermail/jboss-user/attachments/20110323/27f24e69/attachment-0001.html 


More information about the jboss-user mailing list