[jbosstools-dev] Getting 3.3.0.M2 ready for June/AS 7 launch
Snjezana Peco
snjeza.peco at gmail.com
Fri May 27 06:09:17 EDT 2011
Max Rydahl Andersen wrote:
> Hi,
>
> AS 7 Final is planned to be done end of June, and so is Eclipse Indigo (3.7) meaning
> getting a 3.3.0.M2 out in the planned timeframe - we had set 3.3.0.M2 currently planned to be released on 22nd
> (same day as AS 7 and Eclipse 3.7 is going out)
>
> Currently Jira has 148 issues open for this release - and almost none on the future releases.
>
> I'm sure you don't all expect to do all 148 issues for M2 and then do nothing for M3, Beta1, Beta2 and CR1.
> Could you *please* go over your assigned and component issues and state which ones you are going
> to do for M2 and which you are moving of to later ?
>
> That would make it possible to actually see what needs to be done for the release much easier for everyone.
>
> When you do this please remember that 3.3.0.M2 has the primary goals of:
>
> * Running on Eclipse 3.7 final release (i.e. the maven/m2e is currently broken)
>
Maven/m2e problem can be easily fixed.
It is enough to create locally a m2eclipse-wtp update site compatible
with m2e-core placed in the JBT 3.7 TP and include that update site to
the JBT 3.7 TP.
Snjeza
> * Work with AS 7 (start/stop/debug/run/deploy)
> * Not suck
>
> Thus if you are about to do major rework of some components and don't feel you can have it ready in
> a not-suck state please do your work in a branch and merge it back to trunk *after* M2.
>
> And those issues that does that are perfect candidates to have their jira fix version updated to M3.
>
> Thank you!
> /max
> http://about.me/maxandersen
>
>
>
>
> _______________________________________________
> jbosstools-dev mailing list
> jbosstools-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/jbosstools-dev
>
>