[jbosstools-dev] Codefreeze for Beta2 is tomorrow
Max Rydahl Andersen
max.andersen at redhat.com
Thu Nov 15 08:28:10 EST 2012
btw. I've update the jira schedule page now.
Nick/Denis - don't forget you guys should update these too when release dates/names are shuffled ;)
/max
On 15 Nov 2012, at 14:14, Max Rydahl Andersen <max.andersen at redhat.com> wrote:
> There is no CR2 planned at this time. We introduced a Beta2 instead.
>
> GA is planned to go out before end-of-year/face-2-face.
>
> So for now GA is the next - but it will be named CR2 in builds until we consider it ok to go.
>
> /max
>
>
> On 15 Nov 2012, at 12:34, Martin Malina <mmalina at redhat.com> wrote:
>
>> So then 30th Nov is the corefreeze for CR2, right?
>>
>> -Martin
>>
>> On 15. 11. 2012, at 12:22, Max Rydahl Andersen <max.andersen at redhat.com> wrote:
>>
>>> CR1 - sorry mistyped.
>>>
>>> On 15 Nov 2012, at 11:52, Max Rydahl Andersen <max.andersen at redhat.com> wrote:
>>>
>>>> Hi guys,
>>>>
>>>> Just a reminder that Beta2 codefreeze is tomorrow - just as according to the plan you can always see on https://issues.jboss.org/browse/JBIDE#selectedTab=com.atlassian.jira.plugin.system.project%3Aversions-panel
>>>>
>>>> CR1 is planned for codefreeze at 30th Nov which should only be absolute critical bugfixes.
>>>>
>>>> if any questions don't hesitate to ask.
>>>>
>>>> Thanks,
>>>> /max
>>>
>>>
>>> _______________________________________________
>>> jbosstools-dev mailing list
>>> jbosstools-dev at lists.jboss.org
>>> https://lists.jboss.org/mailman/listinfo/jbosstools-dev
>>
>
>
> _______________________________________________
> jbosstools-dev mailing list
> jbosstools-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/jbosstools-dev
More information about the jbosstools-dev
mailing list